Timeline

2014

March

Completion of preliminary sites and architectural plans for submittable to township

April

Applications to township

July

Public hearing and approval to rebuild
Interviewing of builders

August

Church board passed the rebuilding project and to recommend to congregants

December

Congregational approval to rebuild.
Completion of final site, architectural, and engineering plans
RFP (Request for Proposal) to five builders


2015

January

Review and analyze proposals received from builders

February

Selection and contract a builder.
Receive final Resolution from township.
Apply for permits to build.
Obtain loans to finance the building project

March

Preparation for demolishing and rebuilding such as leasing a trailer, purchasing construction bond and insurance, etc

April

Demolish and begin construction


 

It is anticipated with a completion of 8 to 12 months. Let’s pray for God’s blessing and guidance throughout the demolishing and construction process.